Tel: +44(0)1534 752752

Jersey Airport

Fire Hydrants

Location:

Jersey Airport Western Pump Chamber
Jersey

Client:

Jersey Airport

Start Design:

February 2015

Completion:

May 2015

Project Value:

£125K

Services Provided:

Project Management and Contract Administration.

IPM Limited were appointed by Jersey Airport to Project Manage replacement fire hydrant pumps and associated pipework, valves, electrical works and control system.The pumps are located airside on the airfield in a chamber below ground level, works included ventilation, lighting and roof works.IPM Limited had various tasks which they needed to provide.These include:

  • Obtain client brief and work closely with project team to achieve objectives working within Airport procedures.

  • Issue of tender documentation, marking returned tenders.

  • Establish project programme and monitor progress, provide contract administration services.

  • Monitoring the completion of M&E works, attend testing and commissioning, monitor rectification of defects before final payment.

The project was completed on time meeting the client's requirements and was within budget.

For further information on this project please contact David Mason

Tel: 01534 752754
Email: davidmason@ipm.je

Live chat

Please enter your email, name and a message. We will get back to you as soon as we can

Name


Email Address

Message

Send Message

Sending

Live chat sent

Failed to send live chat

Please reload the page and try again