Tel: +44(0)1534 752752

Wesley Chapel

Location:

Wesley Street
Chapel Development
Jersey

Client:

Lloyds TSB

Start Design:

June 2011

Completion:

July 2013

Project Value:

£9m

Services Provided:

Development Monitoring

IPM Limited were appointed by Lloyds TSB to ensure the build of Wesley Chapel was kept within a budget of £9m.The project consisted of a redevelopment and rebuild to the burnt down chapel in St Helier. The rebuild provides 48 apartments and 9 town houses. The period features have been kept at the front of the property.IPM Limited Limited had various tasks which they needed to provide.These included:

  • Prepare an initial report including a review of the budget, cash flow, programme, procurement strategy, plans and specifications, contract documentation, contractor and consultant appointments, statutory consents, project insurances, environmental and site investigation reports.

  • Provide periodic monitoring of progress throughout the construction period including attendance at site meetings and inspection of the development on a regular basis, monitoring of the costs of the development and approval of interim valuations and providing periodic reports on progress to coincide with drawdown requests from the developer.

  • Monitoring the completion of construction works, attend practical completion and any sectional completions and provide the bank with a list of defects and a final report within a month of completion.

The project was completed ahead of schedule and within the £9m budget.

For further information on this project please contact David Mason

Tel: 01534 752754
Email: davidmason@ipm.je

Live chat

Please enter your email, name and a message. We will get back to you as soon as we can

Name


Email Address

Message

Send Message

Sending

Live chat sent

Failed to send live chat

Please reload the page and try again